Monday, June 17, 2013

Patio Finishing

The masons were here to finish off the patio.  They installed the scuppers to funnel the water off of the patio, fixed the corner that was damaged by the excavator, poured a pad for the AC unit and put the top on the wall.

The GC cleaned up the basement and addition and scheduled electrical inspection for tomorrow.

I finished up the electrical punch list left by the inspector, so hopefully we pass electrical inspection tomorrow.

The HVAC contractor is supposed to be coming back tomorrow so I left a note with the thermostats and the seal tight to connect the AC condensing unit.

Photos of the update below: