Framing Continues

Framing continued today.  They were here from 8 until almost 6:30.  They got alot done, but there are still some issues that need to be resolved.

They did fix the one bedroom window that was framed in the wrong location.

However, the ceiling in the bathroom is supposed to be 8'6" but is only 8'.

The window above the vanity is at 5'6" but is supposed to be at 7'.

They didn't add the door into the master closet.

The transom window into the shower is not framed.  We aren't sure if this will be in the glass door or not.

They added the window in the closet, but it is a little larger than we wanted, but is probably OK.

We called the contractor but he didn't answer.  We left a message.

The toilet door is still too large and additional framing needs to be added.